Drainage Strategy for an extension in Finchampstead, Berkshire

Case study

A drainage strategy for an extension in Finchampstead, Berkshire, prepared for planning and approved.

The constraint

Infiltration testing on site confirmed the ground would not take water, so a soakaway was not an option. That ruled out the top of the drainage hierarchy and set the shape of everything that followed.

What we did

The scheme uses rainwater harvesting, raingardens and attenuation storage.

The numbers

Discharge rate0.75 l/s
Climate change allowance, 1 in 30 year35%
Climate change allowance, 1 in 100 year40%
Onn Point proposed drainage strategy for a single dwelling in Gallowstree Common
A drainage strategy from one of our schemes in this area, approved at planning. Client name and address removed.

The kind of condition this discharges

Wording differs between officers, but a scheme like this one is normally answering a condition along these lines:

No development shall commence until a detailed surface water drainage scheme, demonstrating that surface water will be restricted to greenfield run-off rates for all storm events up to and including the 1 in 100 year event plus an allowance for climate change, has been submitted to and approved in writing by the Local Planning Authority.

The greenfield run-off calculation and the attenuation volume are what answer this one. There is a fuller guide to discharging drainage planning conditions if you want to read up on the process.

Outcome

Hydraulic simulation showed no flooding in the 1-, 30- or 100-year storm events, including the climate change allowance. The scheme was approved at planning.

Every scheme in these case studies was approved — that is the point of the exercise. If you have a drainage condition to discharge, send us the wording and the site address and we will tell you exactly what is needed.

More on drainage design in Finchampstead, Berkshire, browse the rest of our case studies, or see what a drainage strategy involves.