Case Study: Land Off Mayflower Close, Stourport-on-Severn

Drainage Strategy in line with SuDS:

Onn Point were instructed by a local developer to assist lifting conditions relating to drainage on a 4-house development based in Stourport. Our drainage strategy seamlessly integrated SuDS report principles, ensuring that the development aligned with the latest environmental standards and regulations.

Onn Point delivered a full detailed drainage design, suitable for construction along with associated soakaway calculations and construction details. Our drainage design specialist team prioritised sustainability, flood risk using flood risk assessments, and environmental preservation.

OUR WORK

Client Reviews

We are incredibly proud of our customer feedback please read some of our testimonials below.

Posted on Google Google
Andy Kerik profile picture
Andy Kerik
Google star 1Google star 2Google star 3Google star 4Google star 5Trustindex verifies that the original source of the review is Google.
Rob from On Point is exceptionally professional and an all-round great person to work with. We had a very complex project, and he supported us at every stage, helping us navigate all the challenges right through to securing planning permission. I highly recommend this company to anyone needing drainage design or similar services. Thank you so much, Rob — you’re a star!
Posted on Google Google
Ryan Taylor profile picture
Ryan Taylor
Google star 1Google star 2Google star 3Google star 4Google star 5Trustindex verifies that the original source of the review is Google.
Outstanding service from Onn Point, great dialogue throughout the process and extremely fast turnaround to help get my project going quickly.
Posted on Google Google
Nick Puleston profile picture
Nick Puleston
Google star 1Google star 2Google star 3Google star 4Google star 5Trustindex verifies that the original source of the review is Google.
We instructed Rob and his team to design a drainage strategy for our New Build in Plymouth. The LLFA raised several points that needed addressing which Rob made a priority to complete. Even though our Architect wanted to proceed to full planning with a pre condition, Rob eventually managed to address all points raised and we now have full planning permission approved by the LLFA. Our build is very complex and Rob overcome every hurdle. We can’t thank Rob and his team enough for their dedication and expertise.
Posted on Google Google
ashley Cook profile picture
ashley Cook
Google star 1Google star 2Google star 3Google star 4Google star 5Trustindex verifies that the original source of the review is Google.
Fantastic company Rob & his colleagues helped me with a condition I had on my planning. He kept me informed all the way through the process & was very thorough. The condition was lifted with all his help. I would not hesitate to recommend Rob & his colleagues.
Posted on Google Google
Malcolm Aitken profile picture
Malcolm Aitken
Google star 1Google star 2Google star 3Google star 4Google star 5Trustindex verifies that the original source of the review is Google.
We needed a surface water drainage plan to satisfy a pre commencement planning condition. Onn Point Civil Engineering produced a very good report which was approved by the local council and at a sensible price too
Posted on Google Google
Christopher Hughes profile picture
Christopher Hughes
Google star 1Google star 2Google star 3Google star 4Google star 5Trustindex verifies that the original source of the review is Google.
Highly recommended drainage specialists, flawless, great communication and very thorough. I will be using Onn Point again for further work early 2025.
Posted on Google Google
Tim Lamont profile picture
Tim Lamont
Google star 1Google star 2Google star 3Google star 4Google star 5Trustindex verifies that the original source of the review is Google.
I fully recommend Onn-Point Civil Engineering ltd, we used them for retrospective drain planning, SUDS Reports, Percolation Tests & Drainage Design, on our single dwelling construction, in Mid Sussex. Rob and Andrew were extremely supportive and guided us through the process and produced a very comprehensive report, for town planning which was successful for our application. this helped us a great deal/ They are without doubt very experienced in their field. I would use them again. Tim Lamont
Posted on Google Google
Preston Jones profile picture
Preston Jones
Google star 1Google star 2Google star 3Google star 4Google star 5Trustindex verifies that the original source of the review is Google.
Great service. Took the time to explain technical issues with a non professional. Andy and Rob were great. I would definetly recommend.
Posted on Google Google
David Williams profile picture
David Williams
Google star 1Google star 2Google star 3Google star 4Google star 5Trustindex verifies that the original source of the review is Google.
Excellent service, very professional and delivered on time. Very pleased overall, thank you
Posted on Google Google
Liam Devaney profile picture
Liam Devaney
Google star 1Google star 2Google star 3Google star 4Google star 5Trustindex verifies that the original source of the review is Google.
Rob and the team at Onn-Point have been brilliant throughout the process. Friendly, polite and professional. Great communicators and a pleasure to work with
Verified by Trustindex
Trustindex verified badge is the Universal Symbol of Trust. Only the greatest companies can get the verified badge who has a review score above 4.5, based on customer reviews over the past 12 months. Read more

Tell us about your site

Send us the site address and the condition wording, or the planning reference, and we will tell you exactly what is needed. If you do not need us, we will say so.

The engineering behind it

Four dwellings on a site where the ground ruled out the obvious answer before the design started.

Why a soakaway was never an option

The Phase 1 ground report found made ground and a high water table, which took infiltration off the table entirely. That put the scheme straight to a restricted discharge and meant the storage had to be found in the pipework rather than in the ground.

Controlling the discharge

Surface water discharges to the existing public surface water sewer through a 1500mm Hydro-Brake manhole limited to 5 l/s at 1.574m head, with the oversized manhole and pipework providing the attenuation. The connection is fitted with a non-return valve so the public sewer cannot back up into the site, and is subject to Section 106 approval.

Foul drainage

Foul water runs separately to the existing public foul sewer, also under Section 106, across a fifteen-manhole network serving all four plots.

The numbers

DevelopmentFour dwellings
InfiltrationRuled out: made ground and high water table
Flow control1500mm Hydro-Brake, 5 l/s at 1.574m head
AttenuationWithin oversized manhole and pipework
Design event1 in 100 year plus 40% for climate change
Surface water outfallExisting public surface water sewer, S106
ProtectionNon-return valve on the connection
FoulSeparate connection to public foul sewer, S106

Taken from the drawing set for this job. The scheme was approved at planning. Site named by town only; the client’s name and the full address are not published.