Drainage Requirements at Each Planning Stage

Planning stages

The drainage information a planning authority expects is not the same at every stage. Submitting a full detailed design with an outline application usually wastes money; submitting an outline-level strategy with a full application usually gets a condition attached, or a refusal. Knowing which stage you are at is most of the answer.

Outline application

At outline, the authority is asking one question about drainage: can this site be drained at all? Not how, exactly — whether. The layout may not be fixed, and unit numbers may still move.

Typically needed:

  • A drainage strategy in principle — the proposed method of surface water disposal and its justification against the drainage hierarchy
  • A flood risk assessment, where the site is in Flood Zone 2 or 3, is one hectare or more, or has other flooding sources
  • An indication of the likely discharge point and rate
  • Enough storage estimation to show the required attenuation can physically fit on the site

Usually not needed yet: detailed pipe design, manhole schedules, or construction details. Percolation testing is sometimes worth doing early anyway — if infiltration turns out to be impossible, that changes how much land the drainage will occupy, and you would rather know before the layout is fixed.

Full application

With a full application the layout is fixed, so the drainage can be designed properly against it. Authorities vary in how much they want up front — some expect a complete design, others accept a strategy and impose a condition for the detail.

Typically needed:

  • A surface water drainage strategy with supporting calculations for the required return periods and climate change allowance
  • Percolation test results where infiltration is proposed
  • A foul drainage strategy, and a foul drainage assessment (FDA1) where there is no public sewer connection
  • A drainage layout drawing showing runs, storage, controls and outfall
  • A flood risk assessment where the site triggers one
  • Highway access and visibility details where a new or altered access is proposed

Submitting the strategy at application stage rather than accepting a condition is usually the cheaper route overall. A condition adds a separate application, a fee, and up to eight more weeks before you can start.

Reserved matters

Where outline permission is already granted, reserved matters is where the detail lands. The principle of development is settled; what is being approved now is layout, scale, appearance, access and landscaping — and drainage has to work with all five.

Typically needed: a detailed drainage design consistent with whatever the outline strategy promised. This is where problems surface if the outline work was optimistic — if the outline said infiltration and testing later shows clay, the attenuation has to fit into a layout that was drawn without space for it.

Discharge of conditions

A separate application to satisfy conditions already attached to a permission. Most drainage conditions are pre-commencement, meaning you cannot lawfully start until they are discharged.

Typically needed: exactly what the condition asks for and no more. The wording matters — a condition asking for a scheme “based on sustainable drainage principles” is asking for the hierarchy to be evidenced, not just a pipe layout. We work from the condition wording rather than a standard package.

Allow eight weeks for determination on top of the time to produce the information.

Related: example drainage conditions and what they require

Permitted development and householder applications

Smaller works often need less, but not nothing. A single extension rarely needs a full drainage strategy, though it may still need a soakaway designed to BRE 365 if it adds impermeable area, and building regulations apply to the drainage regardless of whether planning does.

Where a site sits in a flood zone, permitted development rights can also be restricted, so it is worth checking before assuming no application is needed.

At a glance

StageDrainage strategyDetailed designPercolation testFlood risk assessment
OutlineIn principleNoAdvisableIf triggered
FullYesUsuallyIf infiltratingIf triggered
Reserved mattersConsistent with outlineYesYes, if infiltratingUsually already done
Discharge of conditionsAs the condition asksAs the condition asksIf referencedIf referenced
HouseholderRarelySoakaway onlyIf soakaway proposedIf in a flood zone

If you are not sure which stage applies, send us the planning reference. We will look it up and tell you what is actually needed rather than quoting for everything.